[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136087,797,1,"单选题","临时用电施工组织设计的主要内容不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现场勘察",false,{"key":16,"text":17,"correct":14},"B","确定电源进线、变电所、配电室、总配电箱、分配电箱等的位置及线路走向",{"key":19,"text":20,"correct":14},"C","进行负荷计算",{"key":22,"text":23,"correct":24},"D","明确施工组织机构及主要成员情况",true,"2020版教材P451 \u002F 2019版教材P439 3.临时用电施工组织设计主要内容应包括：现场勘察;确定电源进线、变电所、配电室、总配电箱、分配电箱等的位置及线路走向;进行负荷计算;选择变压器容量、导线截面积和电器的类型、规格;绘制电气平面图、立面图和接线系统图;配电装置安装、防雷接地安装、线路敷设等施工内容的技术耍求;建立用电施工管理组织机构;制定安全用电技术措施和电气防火措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]