[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136071":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136071,797,1,"单选题","临时用电的用户，对不具备安装计量装置条件的，可按其（）计收电费。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","用电容量、使用时间、市场电价",false,{"key":16,"text":17,"correct":18},"B","用电容量、使用时间、规定电价",true,{"key":20,"text":21,"correct":14},"C","最大容量、工作时间、规定电价",{"key":23,"text":24,"correct":14},"D","用电容量、工作时间、市场电价","2020版教材P453 \u002F 2019版教材P441 （三）临时用电的计量1.临时用电的用户，对不具备安装条件的，可按其用电容量、使用时间、规定的电价计收电费。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]