[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136064,797,1,"单选题","施工单位在使用自备电源前应告知并征得供电部门同意后采取安全技术措施，防止自备电源（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发生停电故障",false,{"key":16,"text":17,"correct":14},"B","遭到外力破坏",{"key":19,"text":20,"correct":21},"C","误入市政电网",true,{"key":23,"text":24,"correct":14},"D","发生用电火灾","2020版教材P450 \u002F 2019版教材P438 3. 工程建设用电办理手续 （5）工程项目地处偏僻，虽用电申请已受理，但自电网引入的线路施工和通电尚需一段时间，而工程又急需开工，则总承包单位通常是用自备电源（如柴油发电机组）先行解。决用电问题。此时，总承包单位要告知供电部门并征得同意。同时要妥善采取安全技术措施，防止自备电源误入市政电网。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]