[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136056,797,1,"单选题","工程建设临时用电方案的审批单位（或部门）是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","施工单位",{"key":22,"text":23,"correct":24},"D","电力部门",true,"2020版教材P451 \u002F 2019版教材P439 (一)工程建设临时用电的准用程序 1.施工单位应根据国家有关标准、规范和施工现场的实际负荷情况,编制施工现场“临时用电施工组织设计”,并协助业主向当地电业部门申报用电方案。 2.按照电业部门批复的方案及临时用电安全技术规范进行临时用电设备、材料的采购和施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]