[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136055,797,1,"单选题","施工现场临时用电工程的定期检查应复测（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对地绝缘值",false,{"key":16,"text":17,"correct":18},"B","接地电阻值",true,{"key":20,"text":21,"correct":14},"C","对地放电值",{"key":23,"text":24,"correct":14},"D","接地电流值","2020版教材P452 \u002F 2019版教材P440 临时用电工程应定期检查。施工现场每月一次，基层公司每季一次。基层公司检查时，应复测接地电阻值，对不安全因素，必须及时处理，并应履行复查验收手续。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]