[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136036,797,1,"单选题","施工单位对非强制性检定的计量器进行检定时，（）检定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应送部门管辖的检定机构",false,{"key":16,"text":17,"correct":14},"B","应送工程所在地地市级以上检定机构",{"key":19,"text":20,"correct":14},"C","应送单位所在地地市级以上检定机构",{"key":22,"text":23,"correct":24},"D","可送工程所在地具有相应资质的检定机构",true,"2020版教材P447 \u002F 2019版教材P435 （4）施工单位的计量检定工作应当符合经济合理、就地就近的原则，计量器具可送交工程所在地具有相应资质的计量检定机构检定。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]