[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136007,797,1,"单选题","工程竣工技术资料的移交必须严格管理,按（ ）执行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同",false,{"key":16,"text":17,"correct":14},"B","施工组织设计",{"key":19,"text":20,"correct":21},"C","建设工程文件归档规范",true,{"key":23,"text":24,"correct":14},"D","设计文件","2020版教材P432 \u002F 2019版教材P420 四、竣工资料的移交 2.凡是列入技术档案的技术文件、资料，都必须经有关技术负责人正式审定。所有的资料文件都必须如实反映工程实施的实际情况，工程技术档案必须严格管理，不得遗失损坏，技术资料按《建设工程文件归档规范》GB\u002FT50328—2014执行。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]