[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136006":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136006,797,1,"单选题","按建设项目达到竣工验收条件的验收方式分,不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目中间验收",false,{"key":16,"text":17,"correct":14},"B","单项工程竣工验收",{"key":19,"text":20,"correct":14},"C","全部工程验收",{"key":22,"text":23,"correct":24},"D","单位工程竣工验收",true,"2020版教材P425 \u002F 2019版教材P414 （2）按建设项目达到竣工验收条件的验收方式分为:项目中间验收、单项工程竣工验收和全部工程竣工验收三类。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]