[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136002,797,1,"单选题","联动试运行前应完成的准备工作不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","完成联动试运行范围内工程的中间交接",false,{"key":16,"text":17,"correct":14},"B","编制、审定试运行方案",{"key":19,"text":20,"correct":14},"C","按设计文件要求加注试运行用润滑油（脂）",{"key":22,"text":23,"correct":24},"D","进行项目可行性分析",true,"2020版教材P420 \u002F 2019版教材P408 6. 准备工作已完成（1） 完成联动试运行范围内工程的中间交接。（2） 编制、审定试运行方案和应急预案。（3） 按设计文件要求加注试运行用润滑油（脂）。（4） 机器人口处按规定装设过滤网（器）。（5） 准备能源、介质、材料、工机具、检测仪器等。（6） 布置必要的安全防护设施和消防器材。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]