[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135987":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135987,797,1,"单选题","施工阶段项目成本控制的要点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","落实成本计划",true,{"key":16,"text":17,"correct":18},"B","编制成本计划",false,{"key":20,"text":21,"correct":18},"C","成本计划分解",{"key":23,"text":24,"correct":18},"D","成本分析考核","2020版教材P347 \u002F 2019版教材P333 施工阶段项目成本的控制要点: （1）对分解的成本计划进行落实 （2）记录、整理、核算实际发生的费用，计算实际成本。 （3）进行成本差异分析，采取有效的纠偏措施 （4）注意工程变更，关注不可预计的外部条件对成本控制的影响",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]