[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135986,797,1,"单选题","机电工程项目成本控制中,在施工准备阶段项目成本的控制要点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","优化施工方案",true,{"key":16,"text":17,"correct":18},"B","分析计划成本",false,{"key":20,"text":21,"correct":18},"C","成本差异分析",{"key":23,"text":24,"correct":18},"D","注意工程变更","2020版教材P347 \u002F 2019版教材P333 二、各阶段项目成本控制的要点：1.施工准备阶段项目成本的控制要点：（1）优化施工方案，对施工方法、施工顺序、机械设备的选择、作业组织形式的确定、技术组织措施等方面进行认真研究分析，运用价值工程理论，制定出技术先进、经济合理的施工方案。（2）编制成本计划并进行分解。（3）做出施工队伍、施工机械、临时设施建设等其他间接费用的支出预算，进行控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]