[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135985,797,1,"单选题","机电工程项目成本控制中,在竣工交付使用时的项目成本控制要点是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计算实际成本",false,{"key":16,"text":17,"correct":14},"B","控制返工返修",{"key":19,"text":20,"correct":21},"C","控制保修费用",true,{"key":23,"text":24,"correct":14},"D","注意工程变更","2020版教材P347 \u002F 2019版教材P333 竣工交付使用及保修阶段项目成本的控制要点（1）工程移交后，要及时结算工程款，进行成木分析，总结经验。（2）控制保修期的保修费用支出，并将此问题反馈至有关责任者。（3）进行成木分析考评，落实奖惩制度。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]