[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135980":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135980,797,1,"单选题","下列原因中,不属于施工进度偏差产生的主要原因是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","供应商违约",false,{"key":16,"text":17,"correct":14},"B","施工图纸修改",{"key":19,"text":20,"correct":14},"C","施工方法不当",{"key":22,"text":23,"correct":24},"D","施工质量检验",true,"2020版教材P326 \u002F 2019版教材P311 施工进度偏差产生的原因：通过实际施工进度与计划进度比较，发现施工进度偏差时，应深入施工现场进行调杳，分析产生施工进度偏差的原因。1.设计单位原因：施工图纸提供不及吋或阁纸修改，造成工程停工或返工，影响计划进度。2.建设单位原因:建设资金没有落实，工程款不能按时交付,影响设备、材料采购，影响施工人员的工资发放，影响计划进度。3.施工单位原因：项目管理混乱，施工计划编制失误，分包单位违约，施工现场协调不好，施工人员偏少，施工方案、施工方法不当等，影响计划进度。4.供应商原因：供应商违约，设备、材料没有按计划送达施工现场，或者送达后验收不合格，影响计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]