[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135979,797,1,"单选题","下列措施中,属于机电工程施工进度控制技术措施的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立控制目标体系",false,{"key":16,"text":17,"correct":18},"B","施工方案优化",true,{"key":20,"text":21,"correct":14},"C","拖工激励措施",{"key":23,"text":24,"correct":14},"D","进度统计与比较","2020版教材P325 \u002F 2019版教材P311 技术措施 （1）为实现计划进度目标,优化施工方案,分析改变施工技术、施工方法和施工机械的可能性。 （2）审查分包商提交的进度计划,使分包商能在满足总进度计划的状态下施工。 （3）编制施工进度控制工作细则,指导项目部人员实施进度控制。 （4）采用网络计划技术及其他适用的计划方法,并结合计算机的应用.对机电工程进度实施动态控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]