[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135978,797,1,"单选题","赢得值参数比较中，施工进度提前、费用节支的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","CV>0，SV>0",true,{"key":16,"text":17,"correct":18},"B","CV\u003C0，SV\u003C0",false,{"key":20,"text":21,"correct":18},"C","CV>0，SV\u003C0",{"key":23,"text":24,"correct":18},"D","CV＜0，SV>0","2020版教材P329 \u002F 2019版教材P314 （1）当费用偏差CV为负值时,表示执行效果不佳,即实际费用超过预算费用即超支。当费用偏差CV为正值时,表示实际费用低于预算费用,表示节支或效率高。（1）当进度偏差SV为负值时,表示进度延误,即实际进度落后于计划进度。（2）当进度偏差SV为正值时.表示进度提前,即实际进度快于计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]