[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135977":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135977,797,1,"单选题","关于赢得值法评价指标的说法,正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当费用偏差（CV）为负值时,表示实际费用小于预算费用",false,{"key":16,"text":17,"correct":14},"B","当进度偏差（SV）为正值时,表示实际进度落后计划进度",{"key":19,"text":20,"correct":21},"C","当费用绩效指数CPI\u003C1时,表示实际费用高于预算费用",true,{"key":23,"text":24,"correct":14},"D","当进度绩效指数SPI\u003C1时,表示实际进度超前计划进度","2020版教材P329 \u002F 2019版教材P314 费用偏差CV分析：（1）当费用偏差CV为负值时，表示执行效果不佳，即实际费用超过预算费用即超支。（2）当费用偏差CV为正值时，表示实际费用低于预算费用，表示节支或效率高。（3）当费用偏差CV=0时，表示项目按计划执行。进度偏差SV分析：（1）当进度偏差SV为负值时，表示进度延误，即实际进度落后于计划进度。（2）当进度偏差SV为正值时，表示进度提前，即实际进度快于计划进度。（3）当进度偏差SV=0时，表明项目进度按计划执行。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]