[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135976,797,1,"单选题","机电工程采用横道图表示施工进度计划的优点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","便于计算劳动力的需要量",true,{"key":16,"text":17,"correct":18},"B","能反映工作的机动时间",false,{"key":20,"text":21,"correct":18},"C","能反映影响工期的关键工作",{"key":23,"text":24,"correct":18},"D","能表达各项工作之间的逻辑关系","2020版教材P322 \u002F 2019版教材P308 横道图施工进度计划编制方法直观清晰，容易看懂施工进度计划编制的意图，便于工程施工的实际进度与计划进度的比较，便于工程劳动力、物资和资金需要量的计算及安排。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]