[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135974,797,1,"单选题","质量管理协调主要作用于质量检查、检验计划与（）要求的一致性。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工进度计划",true,{"key":16,"text":17,"correct":18},"B","工程实体现状",false,{"key":20,"text":21,"correct":18},"C","安装工艺规律",{"key":23,"text":24,"correct":18},"D","作业人员配备","2020版教材P316 \u002F 2019版教材P301 质量管理协调主要作用于质量检查、检验计划编制与施工进度计划要求的一致性，作用于质量检查或验收记录的形成与施工实体进度形成的同步性，作用于不同专业施工工序交接间的及时性，作用于发生质量问题后处理的各专业间作业人员的协同性。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]