[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135973,797,1,"单选题","施工现场内部协调中，与施工作业面安排的协调包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢储罐组装",false,{"key":16,"text":17,"correct":18},"B","氧乙炔装置",true,{"key":20,"text":21,"correct":14},"C","焊后无损检测",{"key":23,"text":24,"correct":14},"D","管道涂装防腐","2020版教材P316 \u002F 2019版教材P301 5.与施工作业面安排的协调 机电工程在同一工作面上由不同专业作业人员在不同时段进行工作，专业间存在作业面交替现象，在交接时应协调好临时设施的共同使用，如脚手架、用电和用水点等，共用机具的移交，如电焊机、氧乙炔装置等，还要协调好已形成的工程实体的成品保护措施。如同一工作面实行两个专业以上的搭接作业，则应协调好开始搭接的作业时间、搭接的初始部位和作业完成后现场的清理工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]