[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135972,797,1,"单选题","施工单位项目部与有合同契约关系的单位间协调包括（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","材料供应单位",true,{"key":23,"text":24,"correct":14},"D","质量监督单位","2020版教材P318 \u002F 2019版教材P303 机电工程项目部与施工单位有合同契约关系的单位间协调：协调单位发包单位、业主及其代表监理单位。材料供应单位或个人。设备供应单位。施工机械出租单位。经委托的检验、检测、试验单位。临时设施场地或建筑物出租单位或个人。其他。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]