[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135971,797,1,"单选题","机电工程项目部对工程分承包单位协调管理的重点内容不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量安全制度制定",false,{"key":16,"text":17,"correct":18},"B","作业计划的安排",true,{"key":20,"text":21,"correct":14},"C","甲供物资分配",{"key":23,"text":24,"correct":14},"D","资金使用调拨","2020版教材P317 \u002F 2019版教材P303 （三）协调管理的重点1.施工进度计划安排、临时设施布置。2.甲供物资分配、资金使用调拨。3.质量安全制度制定、重大质量事故和重大工程安全事故的处理。4.竣工验收考核、竣工结算编制和工程资料移交。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]