[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135964,797,1,"单选题","项目部提出变更申请,经现场设计、建设（监理）单位代表签字同意后生效的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","小型设计变更",true,{"key":16,"text":17,"correct":18},"B","一般设计变更",false,{"key":20,"text":21,"correct":18},"C","重大设计变更",{"key":23,"text":24,"correct":18},"D","特大设计变更","2020版教材P306 \u002F 2019版教材P292 （1）小型设计变更。由项目部提出设计变更申请单，经项目部技术管理部门审核，由现场设计、建设（监理）单位代表签字同意后生效。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]