[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135963,797,1,"单选题","施工中发生以下变化，不需要重新编制或修订施工组织设计的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重大设计修改",false,{"key":16,"text":17,"correct":14},"B","施工方法重大调整",{"key":19,"text":20,"correct":21},"C","项目技术负责人变更",true,{"key":23,"text":24,"correct":14},"D","主要施工机械重大调整","2020版教材P293 \u002F 2019版教材P278 施工组织设计的实施：施工组织设计一经批准，施工单位和工程相关单位应认真贯彻执行，未经审批不得修改，原则的重大变更，须履行原审批手续。原则的重大变更包括：工程设计重大修改；有关法律法规标准规范实施修订和废止；主要施工方法的重要调整；主要施工资源配置的重大调整；施工环境的重大改变等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]