[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135959,797,1,"单选题","下列施工交底内容中，属于施工方案交底的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量、安全、进度目标",false,{"key":16,"text":17,"correct":14},"B","工程的重点和难点",{"key":19,"text":20,"correct":21},"C","操作方法、要领",true,{"key":23,"text":24,"correct":14},"D","主要施工工艺及施工方法","2020版教材P292 \u002F 2019版教材P278 施工方案交底1.工程施工前,施工方案的编制人员应向施工作业人员作施工方案的技术交底。除分项、专项工程的施工方案需进行技术交底外,涉及新产品、新材料、新技术、新工艺即“四新”技术以及特殊环境、特种作业等也必须向施工作业人员交底2.交底内容为该工程的施工程序和顺序、施工工艺、操作方法、要领、质量控制、安全措施等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]