[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135957":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135957,797,1,"单选题","专项工程施工组织设计的编制对象正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量要求高的分部工程",true,{"key":16,"text":17,"correct":18},"B","工艺复杂的关键工序",false,{"key":20,"text":21,"correct":18},"C","多个单位工程组成的单项工程",{"key":23,"text":24,"correct":18},"D","单位或子单位工程","2020版教材P286 \u002F 2019版教材P272 （3）专项工程施工组织设计又称为分部（分项工程施工组织设计，是以分部（分项）工程或专项工程为主要对象编制，对分部（分项工程或专项工程的作业过程起具体指导和制约的作用。通常情况下，对于复杂及特殊作业过程，如难度大、工艺复杂、质量要求高、新工艺和新产品应用的分部（分项工程或专项工程需要编制进一步细化的施工技术与组织方案，因此专项工程施工组织设计也定义为施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]