[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135942,797,1,"单选题","关于施工合同中承包人项目经理的说法,正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理经承包人授权后代表承包人负责履行合同,不须发包人确认",false,{"key":16,"text":17,"correct":14},"B","发包人要求更换承包人项目经理,由此增加的费用由发包人承担",{"key":19,"text":20,"correct":21},"C","承包人项目经理不得同时担任其他项目的项目经理",true,{"key":23,"text":24,"correct":14},"D","承包人项目经理事先通知发包人,可离开施工现场","2020版教材P262 \u002F 2019版教材P248 项目经理不得同时担任其他项目的项目经理，应由承包人确认，项目经理才能经承包人授权后代表承包人负责履行合同。项目经理无权履行职责，发包人有权要求更换项目经理，由此增加的费用和延误的工期由承包人承担。项目经理确需离开施工现场时，应事先通知监理人，并取得发包人的书面同意。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]