[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135939,797,1,"单选题","分包方工作中的停检点应在（）合格的前提下，由总包方检查合格后，总包方报请监理（业主代表）进行检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自检",true,{"key":16,"text":17,"correct":18},"B","交检",false,{"key":20,"text":21,"correct":18},"C","互检",{"key":23,"text":24,"correct":18},"D","分检","2020版教材P266 \u002F 2019版教材P251 3.分包单位工作中的停检点应在自检合格的前提下，由总包单位检查合格后报请监理（业主代表）进行检查。分包单位对开工、关键工序交验、竣工验收等过程经自行检验合格后，均应事先通知总承包单位组织预验收，经认可后由总承包单位通知业主组织检查验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]