[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135930,797,1,"单选题","试运行的技术准备工作不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确认可以试运行的条件",false,{"key":16,"text":17,"correct":14},"B","编制试运行总体计划",{"key":19,"text":20,"correct":14},"C","确定试运行合格评价标准",{"key":22,"text":23,"correct":24},"D","编制试运行物资需要量计划",true,"2020版教材P248 \u002F 2019版教材P234 1.试运行的技术准备工作包括：确认可以试运行的条件、编制试运行总体计划和进度计划、制订试运行技术方案、确定试运行合格评价标准。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]