[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135929":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135929,797,1,"单选题","在项目初步设计前的总体设计应满足（）的需要。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备材料采购",false,{"key":16,"text":17,"correct":14},"B","非标设备制作",{"key":19,"text":20,"correct":21},"C","项目土地征用",true,{"key":23,"text":24,"correct":14},"D","工程施工安装","2020版教材P241 \u002F 2019版教材P227 （3）大型机电工程项目设计，为做好建设的总体部署，在初步设计前，应进行总体设计，应满足初步设计展开的需要，满足主要大型设备、大宗材料的预安排和土地征用的需要。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]