[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135926":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135926,797,1,"单选题","评审有异议的重大设计变更,完善后,最终应由（）裁定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评审会",false,{"key":16,"text":17,"correct":18},"B","业主",true,{"key":20,"text":21,"correct":14},"C","设计单位",{"key":23,"text":24,"correct":14},"D","监理单位","2020版教材P244 \u002F 2019版教材P230 三、2.设计变更经审查后应通过资料管理部门及时转发给有关单位执行，重大的设计变更应召集评审会，评审通过后再执行，若评审中异议较大，要退回设计单位进行完善，最终应由业主裁定。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]