[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135921,797,1,"单选题","某项目由原甲地不改变功能地迁往乙地,乙地并无此项目。乙地称该项目为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","迁建项目",false,{"key":16,"text":17,"correct":18},"B","新建项目",true,{"key":20,"text":21,"correct":14},"C","改建项目",{"key":23,"text":24,"correct":14},"D","复建项目","2020版教材P240 \u002F 2019版教材P226 （5）迁建项目。指将原有单位迁移至异地进行生产或服务，并不改变功能而兴建的工程。如迁至异地无此项目，则应对迁出地视为迁建项目，而对迁入地视为新建项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]