[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135908,797,1,"单选题","工业炉窑砌筑工程施工程序中，工序交接证明书的内容不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隐蔽工程的验收合格证明",false,{"key":16,"text":17,"correct":14},"B","钢结构和炉内轨道等安装位置的主要尺寸的复测记录",{"key":19,"text":20,"correct":14},"C","炉体冷却装置、管道和炉壳的试压记录及焊接严密性试验合格的证明",{"key":22,"text":23,"correct":24},"D","耐火材料验收合格的证明",true,"2020版教材P162 \u002F 2019版教材P151 工序交接证明书应包括下列内容：（1）炉子中心线和控制标高的测量记录以及必要的沉降观测点的测量记录；（2）隐蔽工程的验收合格证明；（3）炉体冷却装置、管道和炉壳的试压记录及焊接严密性试验合格的证明；（4）钢结构和炉内轨道等安装位置的主要尺寸的复测记录；（5）可动炉子或炉子可动部分的试运转合格的证明；（6）炉内托砖板和锚固件等的位置、尺寸及焊接质量的检查合格证明；（7）上道工序成果的保护要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]