[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135879,797,1,"单选题","大型原油罐绝热层施工中，依托焊接在罐壁上的保温支架，将绝热材料制品绑紧、定位的施工方法是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拼砌法",false,{"key":16,"text":17,"correct":14},"B","充填法",{"key":19,"text":20,"correct":21},"C","捆扎法",true,{"key":23,"text":24,"correct":14},"D","粘贴法","2020版教材P153 \u002F 2019版教材P142 1.捆扎法 （1）捆扎法是把绝热材料制品敷于设备及管道表面，再用捆扎材料将其扎紧、定位的方法。适用于软质毡、板、管壳，硬质、半硬质板等各类绝热材料制品。 （2）配套的捆扎材料有镀锌铁丝、包装钢带、粘胶带等，此方法最适合于管道和中、小型圆筒设备的绝热。对泡沫玻璃、聚氨酯、酚醛泡沫塑料等脆性材料不宜采用镀锌铁丝、不锈钢丝捆扎，宜采用感压丝带捆扎，分层施工的内层可采用粘胶带捆扎。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]