[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135864,797,1,"单选题","下列做法中，不符合金属热喷涂分层喷涂要求的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","涂层厚度大于0.1mm",false,{"key":16,"text":17,"correct":18},"B","上下两层喷涂方向应相反",true,{"key":20,"text":21,"correct":14},"C","每一涂层均应平行搭接",{"key":23,"text":24,"correct":14},"D","同层喷涂方向应一致","2020版教材P151 \u002F 2019版教材P140 金属热喷涂层（1）施工前，应对热喷涂设备进行检查和试验。（2）基体表面处理等级及粗糙度符合规定。工艺参数应经喷涂试验和涂层的检验优化确定。（3）设计厚度等于或大于0.1mm的涂层应分层喷涂。分层喷涂时，喷涂的每一涂层均应平行搭接，搭接尺寸符合要求；同层涂层的喷涂方向宜一致；上下两层的喷涂方向应纵横交叉。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]