[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135827,797,1,"单选题","自动化仪表工程施工中，综合控制系统设备安装前应具备的条件不包括（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基础底座安装完毕",false,{"key":16,"text":17,"correct":14},"B","地板、顶棚、内墙、门窗施工完毕",{"key":19,"text":20,"correct":21},"C","综合控制系统的行程试验合格",true,{"key":23,"text":24,"correct":14},"D","供电系统及室内照明施工完毕并已投入运行","2020版教材P141 \u002F 2019版教材P130 综合控制系统设备安装前应具备下列条件：（1）基础底座安装完毕；（2）地板、顶篷、内墙、门窗施工完毕；（3）空调系统已投入运行；（4）供电系统及室内照明施工完毕并已投入运行；（5）接地系统施工完毕，接地电阻符合设计规定。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]