[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135826,797,1,"单选题","直接安装在管道上的自动化仪表，宜在（）安装。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管道吹扫后、压力试验后",false,{"key":16,"text":17,"correct":14},"B","管道吹扫前、压力试验前",{"key":19,"text":20,"correct":14},"C","管道吹扫前、压力试验后",{"key":22,"text":23,"correct":24},"D","管道吹扫后、压力试验前",true,"2020版教材P138 \u002F 2019版教材P128 （4）直接安装在管道上的仪表.宜在管道吹扫后安装.当必须与管道同时安装时.在伴通吹扫前应将仪表拆下。 （5）直接安装在设备或管道上的仪表在安装完毕应进行压力试验。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]