[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135805,797,1,"单选题","发电机设备的正确安装程序应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定子就位→定子及转子水压试验→发电机穿转子→氢冷器安装→端盖、轴承、密封瓦调整安装→励磁机安装→对轮复找中心并连接→整体气密性试验",true,{"key":16,"text":17,"correct":18},"B","定子就位→定子及转子水压试验→发电机穿转子→氢冷器安装→励磁机安装→端盖、轴承、密封瓦调整安装→对轮复找中心并连接→整体气密性试验",false,{"key":20,"text":21,"correct":18},"C","定子就位→发电机穿转子→定子及转子水压试验→端盖、轴承、密封瓦调整安装→氢冷器安装→对轮复找中心并连接→励磁机安装一整体气密性试验",{"key":23,"text":24,"correct":18},"D","定子就位→发电机穿转子→定子及转子水压试验→氢冷器安装→端盖、轴承、密封瓦调整安装→励磁机安装→发电机穿转子→对轮复找中心并连接→整体气密性试验","2020版教材P127 \u002F 2019版教材P117 定子就位→定子及转子水压试验→发电机穿转子→氢冷器安装→端盖、轴承、密封瓦调整安装→励磁机安装→对轮复找中心并连接→整体气密性试验等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]