[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135801,797,1,"单选题","低压内缸组合安装正确的过程是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","低压内缸就位找正，隔板调整，转子吊入汽缸并定位，通流间隙调整",true,{"key":16,"text":17,"correct":18},"B","隔板调整，低压内缸就位找正，转子吊入汽缸并定位，通流间隙调整",false,{"key":20,"text":21,"correct":18},"C","低压内缸就位找正，转子吊入汽缸并定位，隔板调整，通流间隙调整",{"key":23,"text":24,"correct":18},"D","低压内缸就位找正，隔板调整，通流间隙调整，转子吊入汽缸并定位","2020版教材P125 \u002F 2019版教材P115 低压内缸组合包括：当低压内缸就位找正、隔板调整完成后，低压转子吊入汽缸中并定位后，再进行通流间隙调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]