[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135800":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135800,797,1,"单选题","锅炉受热面安装程序中，“通球试验与清理”的紧前工序是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备清点检查",false,{"key":16,"text":17,"correct":14},"B","联箱找正划线",{"key":19,"text":20,"correct":21},"C","合金部件光谱复查",true,{"key":23,"text":24,"correct":14},"D","管子对口焊接","2020版教材P121 \u002F 2019版教材P110 锅炉受热面的施工程序为：设备及其部件清点检查→合金设备（部件）光谱复查→通球试验与清理→联箱找正划线→管子就位对口焊接→组件地面验收→组件吊装→组件高空对口焊接→组件整体找正等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]