[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135796":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135796,797,1,"单选题","发电机设备安装程序中，定、转子水压试验的紧后工序是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","定子就位",false,{"key":16,"text":17,"correct":14},"B","氢冷器安装",{"key":19,"text":20,"correct":21},"C","穿转子",true,{"key":23,"text":24,"correct":14},"D","整体气密性试验","2020版教材P127 \u002F 2019版教材P117 发电机设备的安装程序是：定子就位→定子及转子水压试验→发电机穿转子→氢冷器安装-端盖、轴承、密封瓦调整安装→励磁机安装→对轮复找中心并连接→整体气密性试验等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]