[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135795,797,1,"单选题","发电机转子穿装前应进行单独（）试验,试验压力和允许漏气量应符合制造厂规定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通气",false,{"key":16,"text":17,"correct":14},"B","真空",{"key":19,"text":20,"correct":14},"C","气压",{"key":22,"text":23,"correct":24},"D","气密性",true,"2020版教材P127 \u002F 2019版教材P117 发电机转子穿装前进行单独气密性试验，重点检查集电环下导电螺钉、中心孔堵板的密封状况，消除泄漏后应再经漏气量试验，试验压力和允许漏气量应符合制造厂规定。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]