[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135789":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135789,797,1,"单选题","发电机转子穿装工作，必须在完成机务、电气与热工仪表的各项工作后，会同有关人员对定子和转子进行最后清扫检查，确信其内部清洁，无任何杂物并（）后方可进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理同意",false,{"key":16,"text":17,"correct":14},"B","项目总工同意",{"key":19,"text":20,"correct":14},"C","制造商认可",{"key":22,"text":23,"correct":24},"D","经签证",true,"2020版教材P128 \u002F 2019版教材P117 发电机转子穿装工作要求。必须在完成机务（如支架、千斤顶、吊索等服务准备工作）、电气与热工仪表的各项工作后，会同有关人员对定子和转子进行最后清扫检查，确信其内部清洁，无任何杂物并经签证后方可进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]