[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135773":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135773,797,1,"单选题","整体到货的塔器安装,垫铁点焊固定后的后续工作是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基础验收",false,{"key":16,"text":17,"correct":14},"B","吊装塔器",{"key":19,"text":20,"correct":21},"C","二次灌浆",true,{"key":23,"text":24,"correct":14},"D","紧固地脚螺栓","2020版教材P106 \u002F 2019版教材P96 塔器安装程序：塔器现场检查验收→运放至吊装要求位置→基础验收、设置垫铁→整体吊装、找正、紧固地脚螺检、垫铁点固→二次灌浆。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]