[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135772,797,1,"单选题","钢网架结构总拼完成后应测量其挠度值，所测的挠度值不应超过相应设计值的（）倍。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.10",false,{"key":16,"text":17,"correct":18},"B","1.15",true,{"key":20,"text":21,"correct":14},"C","1.20",{"key":23,"text":24,"correct":14},"D","1.25","2020版教材P119 \u002F 2019版教材P109 （3）钢网架结构总拼完成后及屋面工程完成后应分别测量其挠度值，且所测的挠度值不应超过相应设计值的1.15倍。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]