[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135769,797,1,"单选题","球形罐焊后整体热处理应在（）前进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","与球罐壳体连接的受压件焊缝焊接",false,{"key":16,"text":17,"correct":14},"B","无损检测完成",{"key":19,"text":20,"correct":21},"C","压力试验",true,{"key":23,"text":24,"correct":14},"D","气密性试验","2020版教材P115 \u002F 2019版教材P105 （一）整体热处理前的条件 1.已经批准的热处理施工方案。 2.整体热处理前，与球形罐受压件连接的焊接工作全部完成，各项无损检测工作全部完成并合格。 3.加热系统已调试合格。 4.工序交接验收前面工序已经完成，办理工序交接手续。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]