[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135766,797,1,"单选题","钢制储罐充水试验前，所有附件及其他与罐体焊接的构件全部完工并（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","完成中间交接",false,{"key":16,"text":17,"correct":18},"B","检验合格",true,{"key":20,"text":21,"correct":14},"C","质量评定合格",{"key":23,"text":24,"correct":14},"D","经监理确认","2020版教材P112 \u002F 2019版教材P102 充水试验前，所有附件及其他与罐体焊接的构件全部完工并检验合格。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]