[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135763,797,1,"单选题","分两段到货塔器采用在基础上逐段组对安装方式，下列工序顺序正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基础验收、设置垫铁→塔器现场检查验收→运放至吊装要求位置→整体吊装、找正、紧固地脚螺栓、垫铁点固",false,{"key":16,"text":17,"correct":18},"B","塔器现场检查验收→运放至吊装要求位置→基础验收、设置垫铁→整体吊装、找正、紧固地脚螺栓、垫铁点固",true,{"key":20,"text":21,"correct":14},"C","塔器现场检查验收→基础验收、设置垫铁→运放至吊装要求位置→整体吊装、找正、紧固地脚螺栓、垫铁点固",{"key":23,"text":24,"correct":14},"D","运放至吊装要求位置→基础验收、设置垫铁→塔器现场检查验收→整体吊装、找正、紧固地脚螺栓、垫铁点固","2020版教材P106 \u002F 2019版教材P96 塔器安装程序:塔器现场检查验收→运放至吊装要求位置→基础验收、设置垫铁→整体吊装、找正、紧固地脚螺栓、垫铁点固→二次灌浆。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]