[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135760":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135760,797,1,"单选题","某台分馏塔共分三段，采用由下至上逐段组对安装的方法，其第三段（上段）吊装、找正的紧前工序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第二段找正",false,{"key":16,"text":17,"correct":18},"B","第一、二段段间环焊组对焊接",true,{"key":20,"text":21,"correct":14},"C","第二、三段段间环焊组对焊接",{"key":23,"text":24,"correct":14},"D","紧固地脚螺栓","2020版教材P106 \u002F 2019版教材P96 （1）采用正装法，即在基础上先安装下段，由下至上逐段组对焊接的立式安装程序。 （2）—般常见塔器安装组焊顺序：分段筒体、部件检查验收→基础验收、安放垫铁→塔体的最下段（带裙座段）吊装就位、找正→吊装第二段（由下至上排序）、找正→组焊段间环焊缝、无损检测→重复上述过程：逐段吊装直至吊装最上段（带顶封头段）、找正、组焊段间环焊缝、无损检测→整体找正、紧固地脚螺栓、垫铁点固及二次灌浆→内固定件和其他配件安装焊接→耐压试验、气密性试验。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]