[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135751,797,1,"单选题","在气压试验合格后，管道真空系统还应按设计文件规定进行的真空度试验，对管道系统抽真空，达到设计规定的真空度后，关闭系统（）后系统增压率不应大于5%。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7h",false,{"key":16,"text":17,"correct":14},"B","14h",{"key":19,"text":20,"correct":21},"C","24h",true,{"key":23,"text":24,"correct":14},"D","48h","2020版教材P102 \u002F 2019版教材P92 真空度试验按设计文件要求，对管道系统抽真空，达到设计规定的真空度后，关闭系统，24h后系统增压率不应大于5%。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]