[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135742,797,1,"单选题","对非金属管道的连接，在编制连接作业工艺文件前应咨询（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程监理",false,{"key":16,"text":17,"correct":14},"B","建设单位",{"key":19,"text":20,"correct":21},"C","生产厂家",true,{"key":23,"text":24,"correct":14},"D","技术监督部门","2020版教材P95 \u002F 2019版教材P85 对非金属管道的连接，在编制连接作业工艺文件前应咨询生产厂家",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]